70% to Go Until Completion!

70% to Go Until Completion!

The construction phase of Century City Urban Square is well underway, with the foundations and lower levels of the various buildings now visible to passersby, and contractor Murray & Roberts now progressing beyond the first floor in some regions of the development.

117 of the projected 397 construction days have now elapsed, that’s one third down, and two thirds to go on the way to completion! The labour force is 320 strong, with 40440 hours having been worked in the past month alone! Murray & Roberts plans to increase the workforce even more before the Christmas break.